Project
Name:
SBEC Review of Strategic Plan & draft of
new Strategic Plan |
Country:
Samoa |
|
Project
Location within Country:
Apia
_________________________________________
Name of
Client
NZAID/Small Business Enterprise Center (SBEC)
|
Professional staff provided by your Company:
No. of
Staff: 1
No. of
Man-months:
1. 5 |
|
Start
Date: (Month/Year)
3 November
2003
|
Completion
Date: (Month /Year)
23 December
2003 |
|
Name of
associated firm(s) if any:
None |
No. of
man-months of professional staff provided by associated firm(s):
None |
|
Name of
Senior Staff (Project Director/Coordinator: Team Leader) Involved and
function performed:
Co Managing
Director – Overseeing final report
HR Consultant
– As described in actual services provided. |
|
Detailed
Narrative Description of Project:
§
To identify the achievements
and any short-comings in relation to the strategic objectives and issues as
outlined in the current Strategic Plan
§
To produce a new draft
Strategic Plan for 2004-09 |
|
Detailed
Description of Actual Services provided by your Company:
-
Conducted a stock take of existing documentation
related to the 1997-2002 Plan incorporating the findings of the NZAID
Review in 2002.
-
Assessed the impact and effectiveness of the four
strategies and reviewed the achievements/shortcomings of the current plan
in the current Plan through constant consultation with the director of
SBEC, review of board minutes, annual reports/Work Plans, and past
Strategic Plans, as well as consultations with Board members, SBEC staff
and key stakeholders.
-
Drafted a new Plan for 2004-09 based on the findings of
the review.
|