PROJECT DATA SHEET 1998

Project Name:

Tariff Review : Electric Power Corporation

Country:

Samoa

Project Location within Country:

Apia, Samoa

_______________________________________

Name of Client

Electric Power Corporation, Government of Samoa

Professional staff provided by your Company:

Principal Consultant

Financial Analyst

Investment Analyst (2)

No. of Staff: 4

No. of Man-months: 3

Start Date: (Month/Year)

October 1997

Completion Date: (Month /Year)

April 1998

 

Name of associated firm(s) if any:

Pacific Corporate Services Ltd (PCS)

No. of man-months of professional staff provided by associated firm(s):

1

Name of Senior Staff (Project Director/Coordinator: Team Leader) involved and function performed:

 Project Director

 Financial Analyst

 Investment Analyst

 Investment Analyst

Detailed Narrative Description of Project:

Review of existing financial and socio-economic objectives of EPC and examine whether they are adequate and relevant to the requirements of the Government, the EPC and its lending agencies .

Review the relevance and efficiency of the existing tariff structure and level in order to improve the financial position of the EPC to meet its financial and socio-economic objectives.

Detailed Description of Actual Services provided by your Company:

Refer to above.